Republican unitary industrial Enterprise Kobrin Spinning and Weaving Mill «Ruchajka» |
| А. Project Opportunity Description |
|
|
| А1
Project Name |
Modernisation of pryadilnogo proizvodstva na RUPP Kobrin Spinning and Weaving Mill «Ruchajka» |
(а) Short
name: |
|
(b) Full name: |
Modernization of equipment of spinning production at Republican Manufacturing Unitary Production ”Kobrin Spinning Weaving Mill” Ruchajka” |
(c) Summary description |
The aim of the project is to satisfy the needs of domestic and foreign markets in combed yarn and carded yarn of high quality with density 8-20 tex. |
| А2
Progress status |
Technical and economical analysis of project were done, pre-investment stage, the list of basic equipment is determined. In search for investor. |
| А3
Organizations involved and their roles (specify contact persons,
phone, fax, e-mail address, web-page, etc.): |
(а) |
|
(b) |
|
(c) |
|
| А4
Project Description (approach, objectives, components, outputs,
phases, duration, total financing, benefits; transition impact,
technical cooperation, etc.) |
The existing spinning equipment at the enterprise is outdated and couldn’t satisfy the demand of consumers in quality |
| А5
Background/history/overall program/related or similar projects: |
”Kobrin Spinning Weaving Mill” Ruchajka” was founded in 1980. The production was intended for outputting yarn out of synthetic and artificial fibre of different density up to 3 th. tons of yarn and 12 mln. Meters.
|
| А6
Environmental impact summary: |
The enterprise leads the direct job for minimization of bad environmental impact. |
| А7
Possible obstacles/problems/risk assessment: |
Minimal risk degree |
| А8
Project realization and payback period (years) |
1 year, payback period 5 years |
| А9
Industry |
Textile industry |
| B. Capital Cost Items (investment
requirements for project) |
B1 Project
physical components: |
B2 Capital cost |
Designing, cost of equipment, construction and installation works
|
|
| TOTAL (this total must equal the sum of C2+D4)
2070 (th.usd) |
| B3 Sub-projects by location (adding up to the same total as
B2) |
B4 Project cost |
|
|
| C. Capital Resources Available |
C1. Resources,
grants, investments, equity / ownership, etc., tentatively
or firmly arrangents |
C2. Amount: |
| |
|
| D. Required Financial Assistance |
D1. Financing
gaps, type of financial assistance required (loan, equity,
…), rationale/ basis for choice of financial sources and instruments |
kredit |
| D2. Sources of finance (short names) |
D3. Type of instrument |
D4. Amount |
| Borrowed funds |
Credit |
|
D5. Financial institutions
(sources of finance) full names and ditails (addresses in
A3) |
|
| E. Demand (users) and revenues |
E1. Type
of users/ markets, volumes, pricing, revenues, quantifiable
benefits/ savings: |
Domestic market, export to Russian federation. The lowing of cost price, increasing of export |
E2. Revenues (sales) |
|
E3. Amount |
|
| F. Operating and Maintenance
Cost |
F1. Cost
components, strategies for cost recovery, operating organization,
subsidies, etc.: |
|
F2. Cost Item |
F3. Amount |
| |
|
G1. Net
Income Value (market revenues minus operating |
1238(th.usd) |
G2. Amount |
|
| H. Project information source |
H1. This
form was completed by: |
Vice director Andrejuk Zinaida V. |
H2. Organization (address): |
Manufacturing Unitary Production” Kobrin Spinning Weaving Mill” Ruchajka” Sovetskaja str., 139 Kobrin town, Brest region, The republic of Belarus |
H3. Tel. / Fax / E-mail: |
(0162)218-02/(0162)276-54/ dox@rucheybelpak.brest.by |
H4. Date: |
|
H5. Supreme organization: |
|
Республиканское унитарное производственное предприятие Кобринская прядильно-ткацкая фабрика «Ручайка» |